A 46.5 MW wind farm in New South Wales (Australia).

Consists of 31 wind turbines and provides enough clean energy to power 36,000 homes. The turbines are located on the privately owned property Walwa, which is predominantly cleared pastoral land. The wind farm site continues to be used for grazing.

  • Project Configuration: 31 x 1.5MW turbines
  • Capacity: 46.5 MW
  • Completion date: May 2011
  • Energy production: equivalent up to 36,000 homes annually
  • Grid connection: new 132kV transmission line connecting to the existing 132kV Yass-Goulburn line
  • CO2 emissions benefit: approximately 160,000 tonnes per annum
  • Tip Height: 110m
  • Project value: $147M AUD
  • Project location: Gunning, NSW, 70 km north-east of Canberra
POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN 2020

Visit our online community hub, where you can ask questions and give us feedback about the project.

Gunning Wind Farm Community Hub

Approximately $20,000 is available annually for sponsorship of community groups and not for profits local to the Mortlake South Wind Farm. Recipients are determined through an application process. Applications for the Small Grants Program open annually from February to March each year.

Find out more

ACCIONA Energía is launching a scholarship program for the Mortake South Wind Farm. Applications for the Scholarship Program open annually from February to March each year. 

Find out more
1800 283 550
gunning@acciona.com